${spinon.layout.jumpToContent}

Salzgitter

Path renovation at Salzgittersee

The section of the lakeside path from Westfalenstraße to behind the Café del Lago is to be renovated.

As there are now many cracks in the asphalt surface in this area, it will be milled off and repaved. In preparation for the asphalt work, the sides of the path must be cleared. For this extensive ground work, the path section must be closed from April 7 to April 17. The work will be completed before the Easter holidays and the torchlight swim, which takes place during this period, and there will be no restrictions during this time.

The asphalt work is expected to take place from 28.04. to 07.05. During this time, the path section will not be closed, but temporary restrictions on use are to be expected. The SRB asks for your understanding.

Explanations and notes