Description
Description
As the operator of a combustion plant (medium-sized combustion plant, gas turbine and internal combustion engine plant) with a rated thermal input of at least 1 MW and less than 50 MW, you are obliged to notify the competent authority in writing or electronically of the intended operation before commissioning. The operation of an existing combustion plant must be notified to the competent authority in writing or electronically by December 1, 2023. The notification must contain the information specified in Annex 1 of the 44th BImSchV. The competent authority will include the installation in its register of installations. You will be informed of the registration by the competent authority.
Until a uniform nationwide registration module is introduced, you can use the table that you can access via the following link: