Description
Description
As the operator of a combustion plant (medium-sized combustion plant, gas turbine plant, or internal combustion engine plant) with a thermal capacity of at least 1 MW and less than 50 MW, you are required to notify the competent authority in writing or electronically of the intended operation prior to commissioning. The operation of an existing combustion plant must be reported to the competent authority in writing or electronically by December 1, 2023. The notification must contain the information specified in Annex 1 of the 44th BImSchV. The competent authority will enter the facility into its facility register. You will be notified of the registration by the competent authority.
Until a nationwide registration module is introduced, you may use the table available via the link below: