Applying for a partial building permit for the construction of a system

With the partial building permit, you can start construction work on building sections before the building permit is issued.

Description

Description

You need a building permit to erect, modify or change the use of a building. You may only start building once you have received the building permit.

If you have already submitted a complete building application and this has not yet been processed, you can obtain a partial building permit. This partial building permit allows you to start work on the excavation pit and certain components or construction phases before the final building permit is issued.

Explanations and notes